Photo report from the investment
Building occupancy permit
Construction progress 31.12.2021
Construction progress 29.11.2021
In progress: The assembly of balustrades in the galleries is in progress. Facade works have been completed. Works on the electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area are in progress. The assembly of the elevator has been completed. The floors of the balconies and the gallery of the mezzanine level were finished. The fence is being assembled. The following connections have been completed and accepted: power, plumbing, MPEC. The construction of the garage resin surface has begun. A garage door has been installed.
Construction progress 27.10.2021
In progress: Installation of balcony railings on all buildings has been completed. The balustrades are being installed in the galleries. Insulation of the building is in progress, together with the installation of elevation bricks on building C and D. The assembly of the door system on building A, B, C and D has been completed. Electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area have commenced. The installation of sanitary, electrical and ventilation systems in the garage has been completed. The assembly of the elevator has started. The floors of the balconies and gallery of the Mezzanine level were finished. The fence is being assembled.
Construction progress 10.09.2021
In progress: Insulation of the building with the assembly of elevation bricks on building C and D, assembly of door system on building A, B, C and D. Assembly of balcony railings in building C. Assembly of gallery railings is in progress. Works on electrical, sanitary and ventilation installations are in progress. Works related to the development of the investment area have started. The garage hall lighting is being installed.
Construction progress 06.08.2021
Completed: Plastering works in building A, B, C and D. Roof covering and roof flashings on building A, B, C and D. Installation of windows for buildings A, B, C and D. Installation of garage door fittings. Freon installations in buildings A, B, C and D were made.
In progress: Thermal insulation of the building and installation of elevation bricks on building C and D, installation of window system on building C and D. Installation of thermal insulation in the garage. The assembly of balcony balustrades for building A and B has started. Floor layers for buildings C and D. Work is underway on the electrical, sanitary and ventilation systems.
Construction progress 13.07.2021
In progress: Plastering works in building C and D, thermal insulation of the building and installation of façade brick on building A, B and D, installation of window system on building B and D. Installation of thermal insulation in the garage has begun. The assembly of balcony railings in buildings A and B has started. The flooring layers of buildings A and B have started to be installed. Electrical, sanitary and ventilation installations are in progress. Freon installation in building A and B was made.
Construction progress 16.06.2021
In progress: Plastering works in building B and C, thermal insulation of the building and installation of façade bricks on building A, B and D, installation of window system on building A, B and D. Electrical, sanitary and ventilation installations are in progress. The installation of thermal insulation in the garage has started.