Completed: Plastering works in building A, B, C and D. Roof covering and roof flashings on building A, B, C and D. Installation of windows for buildings A, B, C and D. Installation of garage door fittings. Freon installations in buildings A, B, C and D were made.
In progress: Thermal insulation of the building and installation of elevation bricks on building C and D, installation of window system on building C and D. Installation of thermal insulation in the garage. The assembly of balcony balustrades for building A and B has started. Floor layers for buildings C and D. Work is underway on the electrical, sanitary and ventilation systems.